iGAS have completed another successful Bio Methane PRS installation, which was commissioned within two days of delivery on site.
- Despatched Thursday 16th March
- Arrived on site Monday 20th March
- Connected to client services & engine Tuesday 21st March (am)
- System run at full load (5Mw / 1000 Nm3/hr Bio Methane) Tuesday 21st March (pm)
Another happy customer and a great example of how factory acceptance testing of modules prior to despatch leads to a fast and successful commissioning of the client installation.